|
|
|
DspEdu 2.1
Harmonic Distortion in Voltages and Currents at Exchange-I Summary of Measurements at Exchange-I Detailed Harmonic Analysis at Exchange-I Does Exchange-I Need Harmonic Filtering? Harmonic Distortion in Voltages and Currents at Exchange-II Summary of Measurements at Exchange-II Detailed Waveform and Harmonic Analysis at Exchange-II Does Exchange-II Need Harmonic Filtering? |
HARMONIC CURRENTS AT TWO TELECOM EXCHANGES - A CASE STUDY
Suresh Kumar. K.S. Department of Electrical Engineering National Institute of Technology Calicut Calicut-673601, Kerala State , India
Department of Telecommunications,Kerala State requested NIT Calicut to
conduct a harmonic study at the telephone Exchanges
located in the Calicut area in order to derive a better
understanding of the harmonic distortions and the level of
neutral currents at those Exchanges and to arrive at recommendations on
remedial measures if needed.
The Power Quality Study conducted at Exchange-I and Exchange-II results in the following recommendations/observations.
The Exchange-I receives Grid Supply at 11kV level and steps it down to 415V level using two 500kVA transformers. Both transformers are used in the normal condition; but they are not paralleled. There are two 250kVA DG Sets to provide standby supply. Only one is run at a time and the other is maintained as standby. The LT supply is regulated at the transformer output by means of 500kVA a.c voltage stabilisers which have 300-460V input range and maintain 415V output within ± 1%. The transformers have 4.3% impedance. A 70kVAr-capacitor installation is used to improve the power factor at this Exchange. The active power demand of the Exchange-I varies between 100kW to 160kW over the day. The load consists of air conditioning plants, lighting, UPS and PC loads, Lifts, Pumps and the Float Charger-Rectifier units called the Plant. The consumption is dominated by the consumption in A/C units and in the Plant. There are 11 Package AC Plants of 10T rating and 10 Window A/C Units of 1.5T rating. The Window A/C units constitute the major single phase load. The UPS & PC load and the Plant load are the distorting loads in the system. The Plant uses phase controlled Thyristor Converters to provide the charging current to the 48V battery banks as well as the load current from the battery node. This Exchange was monitored on 9-12-1999 to study the harmonic distortion contents in voltages and currents during different times of the day. The measurements were performed at the secondary side of Transformer-2 after switching all the loads to this transformer. Measurements were repeated with and without the power factor correction capacitor. The entire Exchange load was put on one of the 250kVA DG Set and harmonic measurements were carried out at the output of the Generator. Also the harmonic distortion in the Plant Feeder was studied separately in detail. At all stages the corresponding Neutral currents were observed for magnitude as well as harmonic content. Summary of Measurements at Exchange-I The Measurements are summarised in the Table below.
Case I - Transformer Secondary, Average Load, Capacitor OFF, Measurement on one cable of a 3-run system-Data shown after multiplication to account for cable paralleling-Cable Balance was bad and hence data is somewhat in error esp. in the power factor. Case II - Transformer Secondary, Peak Load, Capacitor ON, Other comments as in Case I. Case III - DG Set Output Lines, Typical Load, and Measurement by Clamping all the Cables of multi-run Cable together and hence data accurate. Case IV - At Plant Feeder, Measurement by clamping all the Parallel Cables together. The above measurements reveal that about 1/3rd of total consumption takes place in the Plant and this also happens to be the dominant distorting load in the system. The three-run cable that connects the LT side of the transformer to the Main SwitchBoard was not balanced. The layout of the runs was such that the Clamp CT of the Harmonic Analyser Equipment could not get all the three cables in its jaw. Hence the measurement was done on one of the three cables and a multiplication factor of 3.4 was used to arrive at the total current, power etc. in each phase. The factor should have been 3 ideally; but 3.4 had to be used in order to adjust for the cable unbalance. Under these conditions the measured value will be in error by as much as 10% especially in power factor measurement. The system power factor is about 0.73 while on DG Set. The system reactive power will be about 150kVAr under peak conditions. The 70kVAr capacitor at the bus will improve the power factor to about 0.85.This is thought to be sufficient. However if the power factor has to be 0.95 a total of 100kVAr capacitor will be needed and hence an additional 30kVAr has to be installed. Detailed Harmonic Analysis at Exchange-I Detailed waveform observation and harmonic data were stored in the Harmonic Analyser Equipment memory and was analyzed later using the software available along with the Equipment. Fig.1 shows the waveform printouts for the condition in Case I. The Phase Voltages and line currents at the 500kVA transformer secondary and the neutral current at the secondary are shown. The values correspond to one of the cables in a three-run system. Notice that the voltage waveforms are reasonably pure while the current waveforms are perceptibly distorted. The neutral current (total) shows predominantly 50Hz current with the peak in its half cycles explained by presence of single-phase UPS loads in the system. The neutral current level is small and is about 15% of line current typically and is explained by the unbalances in lighting loads, single phase Window A/C loads and UPS loads . No equipment exclusively aimed at improving the current balance or eliminating third harmonic in neutral needs to be installed at this exchange. There is only very little third harmonic in neutral and that does not justify any effort to remove it.
Fig.2 shows the harmonic contents in the line currents as % of fundamental current. The fundamental currents were 297A, 275A and 338A in R, Y and B phases respectively. Higher order triplen harmonics are absent. 5th and 7th harmonics dominate in general.
![]() ![]() ![]()
![]() ![]() Fig.8 shows the distortion content in % of fundamental current. ![]()
The Table below shows the internationally accepted IEEE STD 519 Current
Distortion Limits for Non-Linear Loads. These limits have to be observed
by every power consuming equipment taking more than 50W or so in the European
countries. Also, United States and other North American countries have
imposed similar restrictions on customers who employ non-linear loads.
The Point of Common Coupling in the case of Exchange-I is the transformer
secondary and the net leakage impedance at that point will be about 5%
on 500kVA basis (accounting for the Stabiliser also). And the maximum demand
could be about 250kVA.This gives a figure of 40 for the ratio Isc/IL
at this point of coupling. Thus the harmonic limits are 7% for components
upto 11th, 3.5% for components upto 17th and 8% for
THD. Fig.4 shows that under peak load conditions, R and Y Phase currents
exceed limits in 5th and 13th harmonics and the THD
of currents in all the three phases (13.4%, 10.9% and 10%) exceed the stated
limit of 8%. However, there is no statutory restriction/limits on
the harmonic currents that can be drawn by a non-linear load in this State
as yet.
4. Harmonic Distortion in Voltages and Currents at Exchange-II, Calicut. The Exchange-II receives KSEB Supply at 11kV level and steps it down to 415V level using two 400kVA transformers. Both transformers are used in the normal condition; but they are not paralleled. There are two 500kVA DG Sets and one 200kVA DG Set to provide standby supply. Only one is run at a time and the others are maintained as standby. The LT supply is regulated at the transformer output by means of 400kVA a.c voltage stabilisers which have 300-460V input range and maintain 415V output within ± 0.5%. The transformers have 4.57% impedance. There is no capacitor installation at this Exchange. The active power demand of the Exchange-II varies between 100kW to 160kW over the day. The load consists of air conditioning plants, lighting, UPS and PC loads, Lifts, Pumps and two Float Charger-Rectifier units called the Power Plant and SMPS. The consumption is dominated by the consumption in A/C units and in the Power Plant & SMPS. There are 12 Package AC Plants of 7T rating and 38 Window/Split A/C Units of 1.5T rating. The Window/Split A/C units constitute the major single phase load. The UPS & PC load and the Plant & SMPS loads are the distorting loads in the system. The Power Plant uses half-controlled Thyristor Converters to provide the charging current to the 48V battery banks as well as the load current from the battery node. The SMPS uses Active Power Factor Corrected Switched Mode Power Supply Modules to carry out the same function. The Power Plant has 3 units of 430V/50Hz input 50V, 400A output rating and two of them were functioning at the time of measurement and were delivering 350A and 300A to the 50V battery bus. The SMPS has installed capacity of 8 modules each capable of delivering 200A into 50V-battery node and five modules were functioning at around 160A each at the time of measurement. This Exchange was monitored on 9-12-1999 and 10-12-1999 to study the harmonic distortion contents in voltages and currents during different times of the day. The measurements were performed at the secondary side of Transformer-1 that was supplying the distorting load. The entire Exchange load was put on the 500kVA DG Set-2 and harmonic measurements were carried out at the output of the Generator. Also the harmonic distortion in the Power Plant Feeder was studied separately in detail due to even harmonic content observed in the currents. The SMPS Feeder currents were separately monitored to study the efficacy of such units in improving the power factor and in reducing the current distortion. At all stages the corresponding Neutral currents were observed for magnitude as well as harmonic content. The HT Side voltages and total HT Side currents were captured in an oscilloscope in order to measure the power factor angle and to calculate the HT Side power factor. This became necessary due to a prominent disparity between the power factor measured by the TOD Meter at the HT side and the power factor metered by Harmonic Analysis Equipment at the LT Side. Oscilloscope measurements at the HT Side resolved the issue in favor of the Harmonic Analyser measurement. Summary of Measurements at Exchange-II The Measurements are summarised in the Table below.
Case I - Transformer-1 Secondary, Typical Load, Supplies all the distorting loads. But Transformer-2 was supplying the A/C Plants and some other loads too and it is not included. Case II - DG Set Output Lines, Entire System Load, and Measurement by Clamping one out of 4 parallel cables. Case III - Power Plant Feeder Load Case IV - SMPS Load The system recorded a power factor of 0.86 while on DG Set. The same value was metered at the HT Side by an independent measurement described later. Thus the system power factor is 0.86 and is satisfactory at that level. There is no immediate need for installation of power factor correction capacitors at this Exchange. Detailed Waveform and Harmonic Analysis at Exchange-II. Fig.9 shows the voltage and current waveforms for Case I and the corresponding harmonic content table containing the values of dominant harmonics. The current waveforms show prominent presence of even harmonics. These even harmonic components come from the Power Plant load. ![]() Fig.10 shows the voltage and current waveforms for Case-II when the entire Exchange load is on a 500kVA DG Set. Here also the most dominant harmonic in current is the second harmonic. ![]() IEEE harmonic limits for even harmonics are at 25% of corresponding odd harmonic limits. Thus the harmonic content in the currents at Exchange-II are above the limits allowed by IEEE 519 standard. Fig.11 shows the waveforms of R, Y and B currents drawn by the Power Plant load. These currents are seen to be asymmetric about time axis and contain very high amounts of 100Hz component (about 60% of 50Hz component). See Fig.12 for the harmonic content information of these currents. This Power Plant uses three phase half controlled rectifier (using three thyristors and three diodes plus one output free wheeling diode) with d.c side smoothing inductance. This is an old design strategy and was aimed at reducing thyristor count at a time when the cost of thyristor was high.
Fig.11 Current Waveforms (R,Y,B) in the Power Plant Feeder
But the current in even such a half-controlled converter will have half wave symmetry and will contain only odd harmonics if the d.c side smoothing inductance were high enough. A similar converter was simulated using a circuit simulator to study the effect of d.c side inductance value on the harmonic content of input current. Based on the simulation study (which is not reproduced in this report) it is concluded that the Power Plant at Exchange-II draws large even harmonic current due to insufficient smoothing inductance in the d.c side and consequent discontinuous current operation of the Converter. Harmonic standards are more stringent on even harmonics. And it is difficult (if not impossible) to filter a harmonic component like second harmonic by passive filtering. Passive Filtering works from only 5th harmonic practically. Hence Exchange-II will have to consider replacing the Power Plant with modern units like SMPS Charger or Fully Controlled Thyristor Converter as the only method to comply with the harmonic requirements if and when Utility Authorities impose such requirements. No Harmonic Filters have to be installed at present because the dominant harmonic is second harmonic and it is not easily filtered. Fig.13 shows the R, Y and B currents drawn by the SMPS units and Fig.14 show the harmonic content information of the same currents. The SMPS does a good job of maintaining power factor at close to unity. However the THD in currents drawn in Y and B phases is excessive considering what is practically achievable in SMPS Technology. Notably these two phases draw even harmonics too.
Fig.13 Current Waveforms (R,Y,B) in the SMPS Feeder
The Exchange has excessive even harmonic content in current at the Point of Common Coupling compared to what the IEEE 519 Standard allows. Especially the second harmonic. However there is no stringent harmonic standard to be conformed to at present. Secondly 6 to 8% THD in currents will not cause significant over heating anywhere in the system. Moreover filtering the second harmonic currents by Passive Harmonic Filter is going to be a very costly affair. The system power factor is 0.86 at present and there is no urgent need to add a power factor correction capacitor unless the firm wants to improve the p.f still further for some reason or other. Thus installing a harmonic filter is going to be very costly and ineffective unless it is tuned to 100Hz and its contribution to 50Hz reactive power is really not needed much (since the p.f. is already good enough). Hence Exchange-II does not need a Harmonic Filter at present. The Exchange will have to replace the existing Power Plant with modern equivalents as and when it is called upon to meet statutory specifications on the harmonic currents drawn. No such statutory specifications are in force at present. HT Side Measurements at Exchange-II
It was observed during the Power Quality
Audit at this Exchange that the TOD
Meter was registering a power factor of 0.5 only. The Harmonic Analyser
used by the consultant recorded 0.98 on one transformer and 0.86 when the
entire exchange load was on one of the 500kVA DG Set. There was no reason
for the low p.f recorded by the TOD Meter. However the TOD Meter is new
and hence many more measurements at individual phase level
as well as three phase level were carried out using different instruments
to confirm the value arrived at by the consultant's Harmonic Analyser.
Fig.15 Total HT Side Currents (R,Y,B) at CT Secondary Hence it is concluded that the system power factor is around 0.89 and that the TOD Meter is in error due to some reason and needs to be looked into. 5. Equipment Used in the Harmonic Study
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||